​Wastewater Management Authority (WMA), established in 2000, under the Wastewater Management Authority Act 2000 operates under the aegis of the Ministry of Energy and Public Utilities. The core service of the WMA is the collection and treatment of domestic, commercial and industrial wastewaters for disposal to an environmentally acceptable quality, ensuring the country's sustainable development through the provision of appropriate water pollution standards, wastewater control systems and management services to the entire population of Mauritius. Being responsible for the wastewater sector in Mauritius, WMA manages the public wastewater system, which consists of 591 km of sewer network, 72 pumping stations and 10 treatment plants, including 4 main treatment plants which are located at St Martin, GrandBaie, Baie-du-Tombeau, and Montagne Jacquot. In order to sustain its rapid economic growth and preserve the country's fragile environment, Mauritius has to address environmental issues related to demographic growth and rapid changes in the use of water and land resources. In 2012, Government approved new Master Plan 2014-2033. The objective of the plan is to elaborate a programme for the development and management of waste water in Mauritius for a period of 20 years 2014-2033.

 For more information, please visit the website of​ CWA : https://www.wmamauritius.mu/



Projects by WMA​

​Major Projects of the Was​tewater Management Authority


1. Grand Baie Sewerage Project-Phase I B (Contract WW302W) - Works Contract

Region: Péreybère to Cap Malheureux

No of House Connections: 4500

Funding: Japan International Cooperation Agency (JICA)

Status: Ongoing

Target date for implementation: 19 August 2019 - 19 March 2023

Cost of Project: MUR 2,401 Million (Incl VAT)


 

2. Grand Baie Sewerage Project-Phase I B (Contract WW230C) - Consultancy Services for Surveys, Detailed Design, Preparation of Bidding Documents and Supervision of the Works

Region: Péreybère to Cap Malheureux

No of House Connections: 4500

Funding: Japan International Cooperation Agency (JICA)

Status: Ongoing

Target date for implementation: scheduled for completion on 19 March 2023

Cost of Project:  Rs 177,971,457.35 (Incl VAT)

 

3. West Coast Sewerage Project – Contract WW209R

Region: Albion to Grande Riviere Noire

No. of House Connections: House connections to be determined after feasibility study

Status: Feasibility study stage.

Target Date for implementation: Depending on funding available

Cost of project: Not yet determined


 

4. Pailles Guibies Sewerage Project – Phase II – Contract WW260W

Region: Pailles and Les Guibies  

No. of House Connections: 3000

Funding: Government of Mauritius

Status: works ongoing

Target Date for implementation: 11 September 2019 – 10 January 2023

Cost of project: MUR  980M (Incl.VAT)


 

5. Rehabilitation/provision of Sewerage Infrastructure at Residence Atlee, Curepipe – CHA Phase IV – Contract WW 351W

Region: Residence Atlée, Derby Street, Gustave Collin Street, Les Casernes & Vicinity

No. of House Connections: 607

Funding: Government of Mauritius

Status: Bidding Documents are being finalised

Target Date for implementation: Tentative award by August 2020 for completion by August 2022

Cost of Project: MUR 137 M (Incl. VAT)

Duration: 24 Months



6. Sewerage Project at Camp Rouillard  - Contract WW 334W

Region: Camp Rouillard 

No. of House Connections: 200

Funding: Government of Mauritius

Status: Bids under evaluation at CPB

Target Date for implementation: Tentative award by June 2020 for completion by June 2022

Cost of Project: MUR 150 M (Incl. VAT)

Duration: 24 months

 


7. Sewerage Project at Morcellement Goolamally  - Contract WW 369W

Region: Morcellement Goolamally, Terre Rouge

No. of House Connections: 225

Funding: Government of Mauritius

Status: Bidding Documents are being finalised

Tentative award; August 2020

Duration: 24 Months

Completion: August 2022

Cost of Project: 135.7 M (Incl. VAT)


 

Other projects


8. Valentina Sewerage Project – Contract WW389W

Region: Valentina

No. of House Connections: 75

Funding: Government of Mauritius

Status: works ongoing

Target Date for implementation: Completion by December 2020

Cost of project: MUR 25.5 Million (Incl. VAT)


 

9. Upgrading of sewers from Junction J. Nehru and Edgar Quirin Road to S. Hossen – Contract WW424W

Region: St Paul

Funding: Government of Mauritius

Status: works on going

Target Date for implementation: Tentatively August 2020

Cost of project: MUR 30 Million (Incl. VAT)


 

10. Rehabilitation / Provision of sewerage infrastructure at Residence Malherbes B – Contract WW331W

Region: Malherbes B

Funding: Government of Mauritius

Status: works on going

Target Date for implementation: To be completed in July 2020

Cost of project: MUR 52.3 Million (Incl. VAT)


 

11. Sewerage Project at Camp Caval and Robinson - Contract WW 226C

Region: Camp Caval and Robinson, Curepipe 

No. of House Connections:

Funding: Government of Mauritius

Status: Bidding Documents for Consultancy Services are being prepared

Target Date for implementation: Tentative award for Consultancy services by December 2020

Cost of Project: MUR 18 million (Incl. VAT)


 

12. Residence Rivière du Rempart

Region(s): Rivière du Rempart

Length of Sewer: 570m

No of House Connections: 75

Funding: Government of Mauritius

Status: Feasibility Study and Detailed Design completed and presently under contract closure.

Cost of Project: - Lump Sum of MUR 2,990,000.00 (VAT inclusive) and Provisional Sum of MUR 1,150,000 (VAT inclusive)

 

        • House Connection Projects


           

13. FRAMEWORK AGREEMENT -  Contract WW380W – Design and Construction of House Connections in the Sewered areas of Mauritius.

Region(s): Sewered areas in Mauritius

Length of Sewer: N.A

No of House Connections: 500 Approx. (Per Year)

Funding: Government of Mauritius

Status: Ongoing.

Cost of Project: - 90 Million

 

14. FRAMEWORK AGREEMENT -  Contract WW381W – Sewer Extension works and Sewer Maintenance Work

Region(s): Sewered areas in Mauritius

Length of Sewer: N.A

No of House Connections: N.A

Funding: Government of Mauritius

Status: Ongoing.

Cost of Project: - 90 Million

 

15. Contract WW 335 - Residence Sadally Sewerage Project

Region(s): Residence Sadally, Vacoas

Length of Sewer: 150m of street sewer and 410m sewer in service corridors

No of House Connections: 60

Funding: Government of Mauritius

Status: Defects Liability Period

Cost of Project: - 15,057,742.35 (VAT inclusive)

 

16. Contract WW427W – Construction of rising main and associated works for ENT Hospital at Vacoas.

Region(s):  Vacoas

Length of Sewer: 445 m of 110mm diameter rising main and 20m of gravity pipe

No of House Connections: 1

Funding: Government of Mauritius

Status: Reinstatement works ongoing

Cost of Project: - 5,380,290.35 (VAT inclusive)

 

17. Contract WW432W – Sewer Extension Works

Region(s):  Phoenix, Quatre Bornes and Port Louis

Length of Sewer: 1505 m

No of House Connections: NA

Funding: Government of Mauritius

Status: Ongoing

Cost of Project: - MUR 18,051,947.86 (VAT inclusive)